Define dependencies between Tasks

Display table of contents

Task planning in the Schedule >

Define dependencies between Tasks

You can create dependencies between tasks. The dependencies can be created either in the table or in the Gantt chart. There are 4 different dependency relationships:

Dependency

Explanation

Graphic

FS (Finish-to-Start)

The task starts when the predecessor is finished (normal sequence).

DE-EABeziehung

SS (Start-to-Start)

The task starts only when the predecessor also starts (start sequence).

DE-AABeziehung

FF (Finish-to-Finish)

The task ends when the predecessor is finished (end sequence).

DE-EEBeziehung

SF (Start-to-Finish)

The task ends only when the predecessor starts (jump sequence).

DE-AEBeziehung