Create Inter-Project Links

You can create inter-project links on the Schedule tab as follows:

On the Schedule tab, select the task you want to link.

Right-click on the task. The drop-down menu opens.

Select Inter-Project Links and click on Edit. The Inter-Project Links overview opens.

EN-CreateInterProjectLinks_3

Click on Add.

The Quick Create: Inter-Project Link form appears.

EN-CreateInterProjectLinks_4

 

Complete the Quick Create: Inter-Project Link form.

Provider = Project that provides information to the current project.

Click in the Project field and select the provider project from the drop-down menu.

Click in the Task field and select the task from the provider project from the drop-down menu.

Click in the Relevant Date field and select Start or Finish from the drop-down menu.

Consumer = Current project. Project that receives information from the provider project.

The Project and Task fields are filled in automatically.


Click in the Relevant Date field and select Start or Finish from the drop-down menu.

General

Click in the Buffer Indicator field and select from the drop-down menu how the buffer should be displayed in the Inter-Project Links overview.

EN-BufferIndicator

Click in the Note field to enter a note for linking the tasks.


The project manager of the consumer (current project) is automatically entered in the Owner field.


Click on Save and Close.

The Inter-Project Link has been created.

The Inter-Project Links are displayed in the Inter-Project Links overview.  

EN-InterProjectLinkOverview


The buffer is green if a buffer is available.

The buffer is red if the buffer has been exceeded.