Project Estimates

In this section you will find an overview of the project budget and schedule:

%Completed: Progress of the entire project in percent.  


This field is updated automatically. The progress is calculated on the Schedule tab. (see Progress Indicator)


Start Date: Start date of a project

Click on the calendar icon and select the start date in the calendar.

EN-ProjectEstimates_2

Finish Date: Estimated end date of the entire project. End of the last task in the project plan.


This field is updated automatically. The end date is calculated on the Schedule tab. (see Define Duration of Task)


Total Budget: Total financial framework available for the project.

Total Forecast: Current estimate of the total cost of the project.

Total Actual: Actual costs incurred up to a certain point in time.


Budgets are entered on the Finances tab.


Recalculate Total Budget, Total Forecast and Total Actual:

Click on the calculator icon (1). The Recalculate button appears.

Click on Recalculate. (2)

The value is recalculated.

EN-ProjectEstimates_1

Last Timesheet Rollup: Last summary of the time confirmations of all project members. This field is updated automatically.


Data records can be found under Timesheets. (see Navigation Bar)