Loading source data

Sometimes, you may want to restore your scenario to source data, or you need to update data because of changes in the underlying portfolio or projects.

To complete or update the scenario from source data, there are the following options:

If you want to …

Use function …

Load the actual source data of all portfolio projects and resources into the scenario

Update Scenario

Add portfolio projects that are not in the scenario

Import Projects

Add portfolio resources that are not in the scenario

Import Resources

Update specific scenario projects

Update Projects

Update specific scenario resources

Update Resources


If the value in the Committed column of a project is set to Committed, work data of this project will be updated from the Commitments rows in TPG TeamManager. If TPG TeamManager is not used, the Committed column should be hidden.