Selected project

To focus on a specific project, you can filter out all other projects.


 While this filter is applied, only assignments can be added via the Add Item menu. Filtering via the filter pane will be disabled.


Select the project on the project level or the individual resource level.

Click the Project filter in the Display group of the menu bar.

FilterProject

ArrowDown
SelectedProject

If the project will start in the future and you want the timeline to start with that date, click Scroll to Project.

ScrollToProject

To remove the filter, click the Project filter again.