Bug Fix: Inactive tasks no longer counted in % complete

Display table of contents

PPP Scheduler Changes >

Bug Fix: Inactive tasks no longer counted in % complete

Inactive tasks were incorrectly taken into account in the % complete roll‑up calculation, including during MPP imports. This was not the correct behavior, as inactive tasks should not influence the percentage.

Inactive tasks will no longer be taken into account when calculating the % complete.