The Resource Picker previously displayed effort only for a single day.

It now automatically calculates the correct effort hours based on the task’s duration when a resource is selected - provided the task is in Fixed Units or Fixed Duration mode and is not set to Effort Driven.

By default, the picker still shows 8 hours until a selection is made.