Bug Fix: Switching to Fixed Effort no longer sets values to 0

Display table of contents

PPP Scheduler Changes >

Bug Fix: Switching to Fixed Effort no longer sets values to 0

Previously, when changing a task from Fixed Duration to Fixed Effort while resource assignments were present, adjusting the task’s duration caused the effort value to be set to 0. This behavior has now been corrected.