Bug Fix: Planned Work missing in Long-Term Projects

Display table of contents

PPP Scheduler Changes > Scheduler App >

Bug Fix: Planned Work missing in Long-Term Projects

Fixed an issue where not all planned work was loaded for projects spanning more than five years. Resource plan work is now loaded correctly for these projects.

This fix also ensures that effort values are calculated correctly when using the external scheduling engine, improving synchronization with the Resource Plan.