With this update, TPG Scheduler supports customizable hours per day and days per month values for project calendars that differ from the default values of 8 hours per day and 5 days per week. It is now possible to customize these settings to meet project requirements.
Example: The value for the hours per day is set to 8.5.

▶ A new task that is planned for 1 day has an effort of 8.5 hours instead of the previous default value of 8 hours.

This function can be deactivated by administrators in the settings:
▪Select the “Deactivate user-defined project settings” checkbox.

▶ After the upgrade, this setting is activated by default, i.e. if the default calendar is not configured with 8 hours per day, all projects are automatically rescheduled the next time they are opened!