Budget Planning

Display table of contents

Budget Planning

Labor costs are not calculated automatically in TPG PPP. You can enter financial data on the Financials tab for a cost overview.

Available views in cost planning

There are two different views available in cost planning, which differ in terms of the period displayed:

The monthly view for a single year is the default view.
In this view, costs are planned and displayed on a monthly basis within a calendar year. It is particularly suitable for detailed cost planning within a year.

EN-BudgetPlanningDefaultView

In addition, the Multi-year view is available.
In this view, cost plans are displayed over several years. The Multi-year view facilitates an overview of long-term cost developments and planning across annual boundaries.

EN-BudgetPlanningMultiYearView


The functions of the buttons are the same as in the Resource Plan tab. (see Resource Plan tab - Create Resource Plan manually)

For clarity, the steps are shown using the default view.

The use of the Multi-year view is described in the section Use Multi-year view in Resource Plan.


Add financial data:

Go to the Financials tab.

For each cost item, create rows for the Budget, Forecast and Actual cost types:

Click on New. (1)

Click in the Cost Type cell. A drop-down menu opens.

Click on Budget, Forecast or Actual. (2)

Enter the available budget and the expected costs for each time period of the project.

Click in the cell of the desired time period. (3)

Enter the amount.


Total updates automatically.


EN-BudgetPlanning

Add to or update the actual data and forecasts as the project progresses.


Totals are also displayed on the Project Details tab under Project Estimates. (see Project Details)