Deactivate Task

You can deactivate tasks in the TPG Scheduler. Proceed as follows:

Show the Inactive column. (see Schedule - Table) ▶ Checkboxes appear in the task rows.

Click on the checkbox of the task in the Inactive column.

The task is crossed out in the table view and the task bar is colored gray in the Gantt chart.

EN-TaskInactive_1

Or

Open the information window of the task. (see Define dependencies between Tasks - Information Window)

Click on the Advanced tab. (1)

Click on the Inactive checkbox. (2)

Click on Save. (3)

The task is crossed out in the table view and the task bar is colored gray in the Gantt chart.

EN-TaskInactive_2