Setting baselines

Before moving projects on the timeline to simulate different planning options, a baseline should be saved. Per project one baseline can be set. You can set baselines for all projects of the scenario at once or for specific projects.

To set baselines for all projects, open the Scenario tab.

Click Baselines in the Scenario group of the menu bar.

Select Set Baseline.

SetBaseline

To set baselines for specific projects, select the desired project(s).

SelectProjects

Click Baselines in the Edit group of the Projects tab.

Select Set Baseline.

SetBaseline_2

Baselines are shown in gray in the bar chart:

BaselineBarChart

When the baseline is set, the baseline start date and the baseline finish date are shown in the corresponding columns in the left part of the table.