Gantt Icons

Gantt icons allow you to display additional symbols directly in the Gantt chart. The symbols appear on a specific date within the task and are useful, for example, for highlighting important milestones, delivery dates, or other relevant events.


▶ All required fields are marked with a red asterisk.


➢Click Add item. ▶ The input fields appear.

DE-GanttIcons_2

▪Identifier: Unique technical name of the Gantt icon.

▪Indicator Name: Display name of the Gantt icon.


▶ This name describes the purpose of the icon and can be used, for example, in legends or configuration dialogs


▪Date Field: Name of the task field that contains the relevant date.


▶ The icon is displayed in the Gantt chart on this date.


▪Icon class name: Defines the icon to be displayed, as well as its formatting and color.


▶ This property consists of one or more CSS classes.


DE-GanttIcons_1

Additional editing options:

➢Click the Delete icon to delete a field.

➢Click Add Item to add a field.

Complete the configuration:

➢Click Submit at the very bottom to apply the settings.

DE-Submit